Introduction
Activity List
1. Referral
1.1 Initial Screening
1.2 Discovery Call Preparation
1.3 Placed on Hold
1.4 Not Proceeding
2. Pre-Qualification
2.1 Planning Investigation
2.2 Site Survey
2.3 Moddie Design Pack
2.4 Moddie Design Portal
3. Building Permit
3.1 Scoping
3.2 Standard Documents
3.3 Plan Preparation
3.4 Additional Consents
3.5 Engagement Documents
3.6 Submission
4. Construction
4.1 Product Manufacturing
4.2 Delivery
4.3 Installation
5. Non-Conformance
5.1 Quality Assurance
5.2 Variation
6. Quote
6.1 Quote
6.2 Variation Quote
7. Progress Claim
7.1 Progress Claim
2. Moddie > Pre-Qualification Activity
This activity confirms that the referred lead meets the basic eligibility requirements and that a Moddie installation is viable for their budget and property constraints.
Sub-Activity
Sub-Activity Description
2.1. Planning Investigation
This process is raised when a potential planning issue has been identified and we require written planning advice from council. As it incurs cost, it should only be raised after we have completed initial contact with customer.
2.2. Site Survey
We look at the property to check access, land conditions, and anything that might affect the build.
*** Note this is same process as PSN spa survey, please check if any changes required
*** TO DO
*** Advise whether same process can be used for spas and Moddies (preferable) or if separate processes needed *** Suggest get Bianca to review this.
2.3. Moddie Design Pack
Preparation of Design Pack
2.4. Moddie Design Portal
Preparation of Design Pack